Last edited 31 Aug 2026

Main author

CIAT Website

Domestic projects in Wales: dutyholder responsibilities

Contents

[edit] Introduction

On 27 August 2026, CIAT published guidance reminding members and affiliates providing services on domestic projects in Wales of the dutyholder requirements introduced by the Building etc. (Amendment) (No.2) (Wales) Regulations 2025, which came into force on 1 July 2026, subject to the applicable transitional provisions.

[edit] Assignment of duties by domestic clients

Regulation 11T(1) enables a domestic client to assign the specified duties in regulations 11R(1)–(3), 11V(2)–(5), 11Z4 and 11Z5:

  • to themselves; or
  • to another person.

The assignment must be recorded in a written statement meeting the requirements of regulation 11T(1).The statement must confirm that the person undertaking the duties understands them and is able to carry them out. It must also contain the required project and contact information and applicable signatures.

The statement must be completed:

[edit] Where no assignment is made

Where the domestic client does not make an assignment under regulation 11T(1), regulation 11T(3) provides for the duties in regulations 11R(1)–(3) and 11V(2)–(5) to be carried out by:

This default allocation under regulation 11T(3) does not include the duties in regulations 11Z4 and 11Z5. These are, however, expressly included among the duties that a domestic client may assign under regulation 11T(1).

Members and affiliates should therefore establish precisely which duties have been assigned, which duties apply by default and to whom they apply.

[edit] Appointment of the Principal Designer and Principal Contractor

Where there is more than one contractor, or it is reasonably foreseeable that more than one contractor will work on the project, regulation 11U requires the client to appoint in writing a Principal Designer and Principal Contractor in accordance with that regulation.

Separately, where the domestic client does not make the appointments required by regulation 11U, regulation 11T(4) provides that:

Members and affiliates should therefore distinguish between duties assigned under regulation 11T(1), the default allocation of specified duties under regulation 11T(3), and the default Principal Designer and Principal Contractor provisions under regulation 11T(4).

[edit] Minor work

Regulation 11Z7 provides that a client is not required to comply with Part 2B where the building work or design work consists only of work described in Schedule 4.

Members and affiliates should therefore establish whether the work falls within this provision before advising a domestic client on the duties that apply. This should not be treated as a general exemption from the dutyholder regime simply because a project is small or minor.

[edit] Responsibilities of designers

Under regulation 11Z2(1), a designer must not start design work unless satisfied that the client is aware of the duties owed by the client for the building work to which the design relates under all relevant requirements.

The legislation does not prescribe a particular process by which the designer must notify the client or require the designer to retain written evidence of that notification. Nevertheless, CIAT recommends that members and affiliates explain the relevant duties clearly and, where appropriate, in writing, and retain an appropriate record. This can provide useful evidence of the basis on which the designer was satisfied, before starting design work, that the client was aware of their duties.

Members and affiliates should therefore establish and record:

The Welsh regime therefore gives domestic clients specific flexibility over who undertakes certain duties, but this is accompanied by detailed requirements around assignment, written statements and dutyholder arrangements. Members and affiliates should ensure that the position is established clearly at the outset, properly documented and reviewed if the project arrangements change.

Clear written advice, properly completed statements, defined appointments and appropriate project records can help domestic clients understand their responsibilities and reduce uncertainty for members, affiliates and the wider project team.


This article originally appeared on the AT website on 27 August 2026.

--CIAT

[edit] Related articles on Designing Buildings

Designing Buildings Anywhere

Get the Firefox add-on to access 20,000 definitions direct from any website

Find out more Accept cookies and
don't show me this again